Overhaul of Unit 2 at Nizhne-Tulomskaya HPP (HPP-13) Tuloma & Serebryansky Cascade HPPs TGC-1 JSC started.
NEM JSC specialists began the repair October 06. Major repair of hydroelectric unit, rehabilitation of its main elements and structural components will be done during the overhaul by the know-how means and advanced materials.
The planned completion of the works March 15, 2016
The ongoing operation of Nizhne-Tulomskaya hydro power plant was started July 11, 1938. It was the second power plant built under the GOELRO plan.
Technical Data
Nizhne-Tulomskaya HPP:
Output: 4 x 14 MW
Head: 17,5 m
Speed: 150 rpm
Runner diameter: 3,6 m
|