Work continues on the
reconstruction of spillway of Nizhnetulomskaya HPP.
At present, the
installation of orthotropic slabs of the bridge over the spillway is underway.
Previously, the installation of a shutter and crane runways, as well as a
lifting mechanism 2x50 tons, have been completed. Preparations are continuing
for the installation of a reinforced spillway
gate (cofferdam).
|