Successfully completed the reconstruction of hydro-mechanical equipment
for discharge basin on HPP-2 Nivskiy Cascade JSC "TGC-1".
In Murmansk region specialists of JSC "Nordenergomontazh" completed reconstruction of hydro-mechanical equipment for discharge basin on HPP-2 Nivskiy Cascade JSC "TGC-1". According to the customer's specifications, creation of working drawings were performed, works on reconstruction of hydro-mechanical equipment were completed, including replacement of fast-falling gate, rope mechanism for maneuvering fast-falling gate and trash grilles was adapted, trash grates were made. Manual of mechanical equipment developed and delivered to the customer. All design work was carried out jointly with JSC "SPKTB" Zaporozhgidrostal".
Building and construction works lasted for two months, complex testing of the new equipment carried out, after it was commissioned. It is planned to follow the reconstruction of hydro-mechanical equipment other units HPP-2.
|